MarketWatch.com reported on February 14 that The LPA Group Inc. (LPA), a unit of Michael Baker Corp., has received supplements on existing contracts to replace three bridges over Lake Lanier on Route 369, west of Gainesville. The updated contracts with the Georgia Department of Transportation (GDOT) total $3.3 million.
The work on the projects — which began in December of 2011 — is expected to take three years to finish.
LPA will provide engineering and design services for the projects, including preparation of the environmental document, preliminary and final construction plans, utility coordination, survey database preparation and geotechnical investigations.
Although it would be nice, the updated spans are not expected to resemble London Bridge.